Piling Supervisor Checklist

General Information

Items to Check

*1. A valid LM certificate available and display on the diver cabin.

*2. Operator of the piling machine is trained and competent to handle the machine

*3. Workers working with the machine adequately trained to work with the machine

*4. Operator protected from falling object, steam, cinders

*5. Other workers working with the machine provided with adequate PPE, such as helmets, ear protectors, proper footwear, gloves, etc

*6. Ground condition at the piling area stable

*7. Safety measures such as shoring, bracing or other means in accordance with the design of a professional engineer.

*8. Area of driving operation well and including borehole barricaded?

*9. No defects or damage signs to the lifting gears, lifting appliances, hammer and other parts of the piling machine

*10. No defects or crack lines on the concrete piles to be driven

  • Download PDF

    Download PDF

  • Save to Novade

    Save to Novade

Piling Supervisor Checklist

General Information

Items to Check

*1. A valid LM certificate available and display on the diver cabin.

*2. Operator of the piling machine is trained and competent to handle the machine

*3. Workers working with the machine adequately trained to work with the machine

*4. Operator protected from falling object, steam, cinders

*5. Other workers working with the machine provided with adequate PPE, such as helmets, ear protectors, proper footwear, gloves, etc

*6. Ground condition at the piling area stable

*7. Safety measures such as shoring, bracing or other means in accordance with the design of a professional engineer.

*8. Area of driving operation well and including borehole barricaded?

*9. No defects or damage signs to the lifting gears, lifting appliances, hammer and other parts of the piling machine

*10. No defects or crack lines on the concrete piles to be driven